| Title | Content |
|---|---|
| Project Name | 132/380kv Gis Substation Buildings for Pp13 |
| Owner | Saudi Electricity Co. |
| Main Contractor | Assad Said For Contracting Co., Ltd. |
| Consultant | Worley Parsons |
| Scope of Work | Design, supply, installation, testing commissioning and handing over of electrical small power lighting, HVAC system fire alarm and firefighting system, including FM 200 gas extinguishing, fire hydrant system and portable fire extinguishing system. |
| Contract Value (SR) | SR 37,749,396 |
| Year Of Completion | 2017 |
| Project Location | Dhurma, Saudi Arabia |